BOW BULB / COFFERDAM

Custom cofferdam for bow-bulb repair

A safe, dry underwater work area was created for class-attended steel renewal at an accident-damaged bow bulb.

220×180 CMCofferdam face
80 CMDepth
48 HDelivery time

01 / REQUIREMENT

Field challenge

The 120 × 100 cm renewal required a watertight boundary adapted to the damaged geometry.

02 / METHOD

Applied approach

  1. 01

    A 220 × 180 cm cofferdam with 80 cm depth was designed.

  2. 02

    The top-entry system was installed over the area.

  3. 03

    A dry space was created for the 120 × 100 cm renewal.

  4. 04

    Dive and internal technical teams worked in coordination.

  5. 05

    The operation proceeded under class attendance.

03 / OUTCOME

Customer outcome

The required environment was established and the coordinated operation was delivered within 48 hours.

FIELD RECORD / LINKEDIN

Operation records from the post

Tap any image to view it full size. Customer and vessel identity is not published.

VERIFIED DELIVERY

Delivery and evidence

FACING A SIMILAR CONDITION?

Let’s make your vessel’s condition clear.

Operations Team · +90 532 459 10 81sales@thedeepmen.com